Challenges

  • Blocks come in by m³ while sales are in m², so the yield calculation is done by hand.
  • Vein and colour matching is not recorded, so shipping from the same batch cannot be guaranteed.
  • Cutting and sizing waste is not measured, so the true cost stays unknown.
  • Stock is not kept slab by slab, so nobody sees how much of each size is left.

Workflows

From block to slab

  1. The block is received into stock with its m³ volume, quarry and vein details.
  2. A cutting production order is opened and the resulting slabs are stocked in m².
  3. The yield (m³ → m²) is calculated and the waste is recorded separately.

From sizing to shipment

  1. Slabs are sorted by size and quality grade.
  2. The order is reserved on the condition of a single vein/batch.
  3. At shipment the delivery note is issued with pallet and m² details.

Documents

  • Block intake card (m³ / quarry)
  • Cutting production order
  • Slab stock list (m² / size)
  • Delivery note (pallet / m²)

Reports

  • Yield by block
  • Stock breakdown by vein and batch
  • Cutting waste rate
  • Stock position by size

Metrics

  • Yield ratio (m²/m³)
  • Cutting waste rate
  • Cost per m²
  • Batch consistency rate

Compliance

  • Mining licence and quarry operating permit
  • CE declaration of conformity for construction products
  • Occupational health and safety records (dust, cutting)

Glossary

Block
The raw input received into stock in m³
Yield
The production efficiency that gives the m² obtained from a block
Vein / batch
The lot-tracking field that keeps colour consistent
Size
The variant definition that separates slab stock

FAQ

Can I calculate the yield of a block?

Yes — the m³ in and the m² out are compared on the production order and the yield is reported.

Can I guarantee shipping from the same vein?

Yes — vein and batch details are kept as a lot, and the order is reserved from that same batch.

Can I measure the cutting waste?

Yes — waste is recorded as a separate line item and the rate is produced per block.

Can I see stock by size?

Yes — slabs are separate stock items by size and quality grade.

Can I work out the cost per m²?

Yes — block cost, cutting expense and waste are divided by the m² produced.